arrow_back Back to Certificates
FIDIC Red Book / Standard EPC Contract

INTERIM PAYMENT CERTIFICATE (IPC)

Clause 14.6 • Application for Interim Payment & Engineer's Determination

IPC-01 Ref: IPC-2026-06
Approved
Employer / Client
Skyline Developers Group
client@skylinetowers.pk
Project Title: Skyline Twin Towers - Phase II
Site Location: DHA Phase 8, Karachi
Contract & IPC Timelines
Date of Certification: 05 Sep 2026
Billing Period: Start to 07 Oct 2026
Original Contract Sum: PKR 125,000,000
Resident Engineer: Lead Resident Consultant - NESPAK

Statement of Certified Work & Deductions

Item Description Calculation Basis Amount (PKR)
1. Gross Value of Work Executed (Cumulative to Date) Certified BOQ Measurement PKR 25,000,000.00
2. Less: Retention Money Held against Defect Liability Period (DLP) 5.00% of Gross - PKR 1,250,000.00
3. Less: Mobilization Advance Recovery Pro-rata recovery of contractor mobilization advance 10.00% of Gross - PKR 2,500,000.00
4. Less: Withholding Tax (WHT) Statutory income tax deducted at source 7.50% of Gross - PKR 1,875,000.00
NET AMOUNT CERTIFIED PAYABLE TO CONTRACTOR Clause 14.7 PKR 19,375,000.00
Prepared By (Contractor QS)
Lead Quantity Surveyor
Recommended & Verified By
Lead Resident Consultant - NESPAK
Approved for Payment (Employer)
Project Director / CFO